Hamburg, Germany

Expansion of a sludge incineration plant (Klärschlemmverbrennungsanlage) in Hamburg, Germany

Brief Project Description

The project consists of three new buildings - a fuel reception building (Brennstoffannahme), a steel bridge for transporting processed fuel (Bandbrücke), a multifunctional building (Mehrzweckgebäude), and a steel structure for incinerating the fuel (Kesselhaus).

Our Contribution

Conceptualization, development, and calculation/sizing of all steel structures, including crane beams and brackets.

Creating a 3D model in TEKLA Structures.

Preparing overview drawings of all steel structures, including bracket connections to the concrete structure and embedded elements.

Modelling all connections.

Preparing quantity calculations.

Intensive communication with the equipment design department.

Volume of steel structures

  • 1150 tons of steel
  • 3500 m² GIRO

Implementation Period

  • 2023-2025

The project is being carried out in collaboration with Grebner Ingenieure GmbH, Limburg, Germany, and Ingenierbüro T.Dressel, Bietigheim-Bissingen, Germany.